Microsoft Project Tutorial: Finding Late Tasks with Microsoft Project Custom Filters

microsoft project late takes

Written By Andrew Makar

Professional Cat Herder and an Agile Enthusiast with a keen interest in putting PM theory into actual practice.

In this Microsoft Project Tutorial, you’ll learn how to use a custom filter to find late tasks in Microsoft Project.

When managing a project schedule of even a moderate size, it’s valuable to be able to quickly identify late tasks without scrolling through a large hierarchy of tasks. In Microsoft Project, you can identify incomplete, late, or slipped tasks by using one of these options:

  • Tracking Gantt view
  • Incomplete Tasks filter
  • Late Tasks Assigned to Resource filter
  • Slipped/Late Progress filter

These built-in filters are nice, but I usually need to filter on a different set of criteria to view the data I like to see. So I decided to create a custom filter in Microsoft Project that would identify late tasks.

Finding Late Tasks the Easy Way

My original approach was to identify a late task by filtering on the % Complete field, the Baseline Finish, date, and the Resource name column. I followed these steps:

1. Select the Tracking Gantt View using the Entry Table.
2. Insert Baseline Start and Baseline Finish.
3. Confirm the % Complete column is in the view.
4. Filter on the % Complete column (Figure 1).

Figure 1 - Percent Complete Late Task Filter Microsoft Project

Figure 1 – % Complete Filter

5. Filter on the Baseline Finish date where the Baseline Finish Is Less Than Or Equal To a given status date (Figure 2).

Figure 2 -Baseline Finish filter Late Task Filter Microsoft Project

Figure 2 – Baseline Finish filter

The resulting schedule identifies all the tasks that haven’t finished and can be filtered by resource (Figure 3).

Figure 3 - Late Task Filter Microsoft Project using Auto Filter

Figure 3 – Late tasks using Auto Filter

This approach worked to generate a list of late tasks for project status reviews; however, once I switched views or needed additional information, I had to remove the filter and then rebuild it a few minutes later. This process quickly became tiresome to simply view late tasks. The need for a quick and reusable filter to identify tasks that were behind schedule led me to create a custom filter that I named Behind Schedule.

Finding Microsoft Project Late Tasks the Easier Way:  Behind Schedule filter

You can create your own custom Behind Schedule filter by following these steps:

1. Select Project | Filter For | More Filters and click New.
2. Enter “Behind Schedule” in the Name field.
3. Click the first row in the Field Name and select the Baseline Finish field.
4. Enter “is less than or equal to” as the test condition.
5. Enter “Status Date:”? into the Value field (Figure 4).

(It is important to enter the question mark after the quote value, as this represents a parameter. The text entered between the quotation marks is the actual text that will appear in the dialogue box.)

Figure 4 - Behind Schedule filter Late Task Filter Microsoft Project

Figure 4 – Behind Schedule filter

6. Click the second row and select the % Complete field.
7. Select the “does not equal” Test condition and enter 100% as the value in the Value column.
8. Click the OK button (Figure 5).

Figure 5 - Late Task Filter Microsoft Project

Figure 5 – Building a custom filter

Using the Behind Schedule filter

To use the filter, click the Behind Schedule filter in the Formatting toolbar and select the Project Status date. The filter will identify any incomplete tasks based on a selected date (Figure 6).

Figure 6 - Using Late Task Filter with Microsoft Project

Figure 6 – Late tasks using the Behind Schedule filter

To clear the filter, click the All Tasks in the Filter combo box, and all the project tasks will display.

Three key points about using the custom filter

1. Remember to baseline.
In order for the filter to work, you need to baseline (gasp) the project schedule. If project teams are hesitant to baseline the entire schedule, you should apply a rolling planning approach and baseline the tasks for the next phase or major milestone.

2. Look at Slipping Tasks.
The Behind Schedule filter identifies only tasks that are incomplete and have exceeded the baseline finish date. I encourage you to also look at the Slipping Tasks and Slipped Tasks\Late Progress to identify tasks with impacted start dates.

3. Add the filter to your Global.mpt file for future projects.
The Behind Schedule filter that you created is a local filter that is available only in the current .mpp file. If you want this filter to be available for all your projects, you need to add the filter to your Global.mpt file, which contains all the custom objects for your Microsoft Project files.

To add a custom filter to your Global.mpt file, select Tools | Organizer | Filters, select the Behind Schedule filter, and click the Copy button (Figure 7).

Figure 7 - Adding to the Global MPT

Figure 7 -Adding the Behind Schedule filter to Global.mpt

Conclusion

You can create additional filters based on your criteria by following the steps outlined in this tutorial. If you have a favorite filter or a request for a specific filter, please comment below and I’ll see if I can assist!

For more tutorials on how to use Microsoft Project, check out our list of Microsoft Project tutorials.

Analyze your Microsoft Project Schedule in Minutes

Stop struggling with Microsoft Project and Start Using It to Delivery Your Project

microsoft project schedule analyzer

Learn how to:

  • Slice and dice Microsoft Project data with over 40 custom filters and highlights
  • Run the Schedule Quality Analyzer based on DCMA standards
  • Project Metrics Analyzer provides push button metrics
  • Custom VBA Macros to analyze your schedule and produce meaningful project metrics
  • Bonus #1 Are you ready to baseline checklist?
  • Bonus #2 How to build a 4 week task window tutorial

Recommended Articles

Project Schedule Quality 102:  Finding Invalid Summary Tasks

Project Schedule Quality 102: Finding Invalid Summary Tasks

In this Microsoft Project tutorial, you’ll learn how to identify invalid summary tasks in a project schedule by building custom filters. We want to identify any summary tasks that have a predecessor and any summary tasks that have resources assigned.

Microsoft Project Tutorial: Using Deadlines in Microsoft Project

Microsoft Project Tutorial: Using Deadlines in Microsoft Project

One of the key lessons learned with Microsoft Project is to build a dynamic project schedule. A dynamic schedule is properly sequenced and is free of any task constraints. As the project executes, the Start and Finish dates will adjust based on the actual start/finish and actual work/duration recorded in the schedule.

Share This