Atlassian Confluence Tutorial : Build a Project Portfolio Dashboard

confluence tutorial portfolio status report

Written By Andrew Makar

Professional Cat Herder and an Agile Enthusiast with a keen interest in putting PM theory into actual practice.

In this Atlassian Confluence tutorial, you’ll learn how to build a project status dashboard in 3 easy steps

Atlassian’s Confluence product is an amazingly powerful and flexible collaboration tool that enables distributed teams to build better software products. Confluence is a single collaboration tool where teams can organize, create documents and discuss project work in one single place. Using Confluence, project teams can develop product documentation, track meeting minutes, draw process flow diagrams, mind maps and even create technical architecture documents. In this article, I’ll show you how to build a project portfolio dashboard to manage your projects or programs in a portfolio.

Below is a sample snapshot of a small program with 3 projects. With one glance, I can assess each project’s heath in terms of status, schedule, budget, issues and risks using Confluence’s graphical indicators.

If I click on the project title, I can also drill down to the specific status report for further analysis. The benefit of this solution is program managers can roll up individual status reports into summary level report. If the underlying status report changes, the dashboard is automatically updated.  To create a project portfolio dashboard, follow these steps:

Step 1: Create individual status reports

Step 1.1 Create a table in Confluence and format using the heading column icon.

atlassian confluence tutorial

The table can mimic the fields on your company’s current status report template.  Confluence is flexible so feel free to modify the format as necessary.  Status can be entered just by typing text or content in the cells.  If you want to tag someone simply use the @ sign short cut and tag them.  If you want to specify a date, use the // shortcut key.

Below is the sample status report.

atlassian confluence tutorial

Step 1.2 To add the Status indicators, click on the Insert Macro icon in the toolbar and insert the Status macro.

Format the macro with the desired text and colors.

confluence status macro

Step 1.3 Insert a Page Properties container

Below the status report, you’ll insert a Page Properties macro. It is ok if it appear below the status report since you’ll be cutting and pasting the table into the container in the next step.

confluence page properties

Step 1.4 Cut and paste the table into the Page Properties container

confluence tutorial

Step 1.5 Add a label called “status” to the page

Adding a label is easy. Assuming you’re in edit mode, just click on the tag icon after the page title.

confluence add a label

If you’re not in edit mode, you can always press “L” and the same label dialogue will appear.

confluence labels

Step 1.6 Enter the word “status” for the label, press add, close the dialog box and save the page.

Congratulations you’ve created your first status report template. If you think you’ll be rolling out this template throughout the organization, you’ll want create a global page template in Confluence so others can benefit from your hard work.

Step 1.7 Repeat creating status reports for every workstream or project in the program or portfolio

It quickly becomes a copy and paste exercise!

Step 2 Create the Portfolio Page

With the individual project status report pages created, you want to create a portfolio page that will display the summary view of individual status reports. I prefer to keep all status reports in a single page hierarchy, but you could distribute this template across Confluence pages and Confluence spaces and still develop a portfolio view across multiple pages.

Step 2.1 Insert a Page Properties Report Macro

The Page Properties macro displays a table of pages that contain the Page Properties macro and a specific label. The table will link to each individual page and display specific columns from the status report.

confluence page properties report macro

Step 2.2. Enter the label “status”

confluence page properties with label

Now the report needs to be tailored to only include specific columns on the portfolio status page.

Step 2.3 Click Options – Show and enter the following columns Launch Date, Phase, Overall Status, Schedule, Budget, Issues, Risks

If you have a lot of reports, you can limit the number of items to display by providing a numeric value. I also like to sort by Launch Date. Click the Preview icon to refresh the report summary.

confluence page properties macro

Step 2.4 Click Save to Close the dialogue and Save the page

Step 3 Review the completed Dashboard

With a few clicks, you’ve generated a complete portfolio dashboard with the key traffic light indicators. Remember any row in the status report can be pulled into the summary view by simply typing the field name in the Page Properties report.

It may not seem like much but getting real-time visibility into a portfolio instead of consolidating PowerPoint driven status reports or having to resend a new status report with a last minute change is a time saver. Imagine the time saved if you were running a PMO and had to review 60 projects each week?

In my next Confluence tutorial, I’ll show you how to track a list of action items for headache free meeting minutes!

Learn how to manage your projects BETTER with Atlassian Confluence

Manage projects, programs and portfolios using using Atlassian Confluence

atlassian confluence project management

Learn how to:

  • Managing with a Wiki and the Project Manager’s Dilemma
  • Creating Status Reports and Dashboards
  • Tracking Program Action Items
  • Gantt Charts and Roadmaps
  • Tracking Issues and Risks
  • Managing Project and Program Requirements
  • 1:1 Status Reports