Network Sensitvity and the Critical Path

Print E-mail
Written by Dr. Andrew Makar   

If you've been studying the critical path methodology (CPM) and project schedule development, you may have heard the term network sensitivity. Without going into a lecture on constructing project networks with forward and backward passes, I'll define sensitivity in simple terms.

A project schedule is considered sensitive if the critical path will likely change during project execution. The critical path is simply all the tasks that drive the end date of your project schedule. If your project schedule has multiple critical paths, then your project schedule is considered sensitive. If your project schedule only has one critical path and there is slack among the various tasks, then your project schedule is considered insensitive.

Figure 1 depicts an insensitive network as it only has 1 critical path. (I know it's a simple 5 task example but explaining sensitivity with a 1000 task schedule can be daunting!)

critical path method project schedule


Figure 1 Insensitive Critical Path

Why should the PM care?

Understanding the critical path is useful to know when tracking a project schedule's performance. In Figure 1 above, if Task 4 is late, the project manager will not have to worry as much compared to Task 1, 2, 3 or 5 as these tasks are on the critical path. If any of these tasks are late, then they will have a direct impact on the project's end date. Task 4 has some slack or free time before it affects the project schedule.

Understanding how many critical paths and the available slack in the schedule determines how much time the project manager needs to spend specifically managing the critical path. Project managers already have enough work to do resolving issues, managing vendors, and communicating status in addition to the good practice of weekly project schedule control. Monitoring the critical path is just one more value add task that the project manager needs to consider when monitoring project status.

Attached is the sample project schedule if you'd like to experiment with the duration and slack on the project's critical path.

 