Written by Dr. Andrew Makar
|
|
Tuesday, 30 June 2009 22:26 |
MS Project Tutorial: How to Add a Recurring Task in Microsoft Project
You can add a recurring task in Microsoft Project by following these steps:
1. Select Insert – Recurring Task 2. The Recurring Task Information dialogue box appears

3. Insert the Task Name, Duration, Recurrence Pattern, Start Date and assign any relevant calendar for the task. 4. Press Ok
My 12 week recurring team status meeting on Mondays is configured as follows:

The result is displayed below:

When should you use a recurring task?
Project managers often ask if they should use a recurring task in their project schedules or if they should adopt individiual tasks for the various status meetings. I provided my opinion in a recent post on using Microsoft Project recurring tasks.